1. The expected outturn for earthwork in excavation in ordinary soil per workman per day is
- 1.00 cum
- 2.00 cum
- 3.00 cum
- 4.00 cum
Answer: C
2. The expected outturn of brickwork in cement mortar in the foundation and plinth per mason per day, is
- A. 1.00 m3
- B. 1.25 m3
- C. 1.50 m3
- D. 1.75 m3
Answer: B
3. The brickwork is measured in sq meters, in the case of
- Honeycomb brickwork
- Brick flat soling
- Half brick walls or the partition
- All the above
Answer: D
4. The height of the sink of the wash basin above the floor level is kept
- 60 cm
- 70 cm
- 75 cm to 80 cm
- 80 cm
Answer: C
5. For 12 mm thick cement plaster 1: 6 on 100 sq.m new brickwork, the quantity of cement required is
- 0.200 m3
- 0.247 m3
- 0.274 m3
- 0.295 m3
Answer: C
6. The item of steelwork which is measured in sq.m, is
- Collapsible gates
- Rolling shutters
- Ventilators and glazing
- All the above
Answer: D
7. The damp proof course (D.P.C.) is measured in
- Cub. m
- Sq. m
- Meters
- None of these
Answer: B
8. The volume is measured correctly to the nearest
- 0.01 cum
- 0.02 cum
- 0.03 cum
- 0.04 cum
Answer: A
9. Is 1400 kg/cm2 and bond stress is 6 kg/cm2, If the tensile stress of a steel rod of diameter required bond length of the rod is
- 30 D
- 39 D
- 50 D
- 59 D
Answer: D
Also Read – 100+ Surveying MCQ Questions | Civil Engineering Interview Questions
10. For 100 sq.m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is
- 0.90 m3
- 0.94 m3
- 0.98 m3
- 1.00 m3
Answer: B
11. Size, capacity, and materials need to be specified for
- Bib-cocks
- Stop-cocks
- Ball valves
- All the above
Answer: D
12. The weight of an item is measured correctly to the nearest
- 0.25 kg
- 0.50 kg
- 0.75 kg
- 1.00 kg
Answer: D
13. Berms are provided in canals if these are
- Fully in excavation
- Partly in excavation and partly in embankment
- Fully in embankment
- All the above
Answer: B
14. The expected outturn of half brick partition wall per mason per day is
- 1.5 m 3
- 2.0 m3
- 4.0 m2
- 5.0 m2
Answer: B
15. The floor area includes the area of the balcony up to
- 100 %
- 75 %
- 50 %
- 25 %
Answer: C
16. The slope of the outlet of the ‘P trap’ below the horizontal is kept
- 8°
- 10°
- 12°
- 14°
Answer: D