Estimation and Costing MCQ Questions with Answers | Civil Engineering MCQs

Prepare yourself with these 100+ Estimation and Costing MCQ Questions with Answers. These 100+ Estimation and Costing Interview Questions with Answers will help you in Viva and job interviews.

100+ Estimation and Costing MCQ Questions with Answers

1. The expected outturn for earthwork in excavation in ordinary soil per workman per day is

  1. 1.00 cum
  2. 2.00 cum
  3. 3.00 cum
  4. 4.00 cum

Answer: C

2. The expected outturn of brickwork in cement mortar in the foundation and plinth per mason per day, is

  1. A. 1.00 m3
  2. B. 1.25 m3
  3. C. 1.50 m3
  4. D. 1.75 m3 

Answer: B

3. The brickwork is measured in sq meters, in the case of

  1. Honeycomb brickwork
  2. Brick flat soling
  3. Half brick walls or the partition
  4. All the above

Answer: D

4. The height of the sink of the wash basin above the floor level is kept

  1. 60 cm
  2. 70 cm
  3. 75 cm to 80 cm
  4. 80 cm

Answer: C

5. For 12 mm thick cement plaster 1: 6 on 100 sq.m new brickwork, the quantity of cement required is

  1. 0.200 m3
  2. 0.247 m3
  3. 0.274 m3
  4. 0.295 m3

Answer: C

6. The item of steelwork which is measured in sq.m, is

  1. Collapsible gates
  2. Rolling shutters
  3. Ventilators and glazing
  4. All the above

Answer: D

7. The damp proof course (D.P.C.) is measured in

  1. Cub. m
  2. Sq. m
  3. Meters
  4. None of these

Answer: B

8. The volume is measured correctly to the nearest

  1. 0.01 cum
  2. 0.02 cum
  3. 0.03 cum
  4. 0.04 cum

Answer: A

9. Is 1400 kg/cm2 and bond stress is 6 kg/cm2, If the tensile stress of a steel rod of diameter required bond length of the rod is

  1. 30 D
  2. 39 D
  3. 50 D
  4. 59 D

Answer: D

Also Read – 100+ Surveying MCQ Questions | Civil Engineering Interview Questions

10.  For 100 sq.m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is

  1. 0.90 m3
  2. 0.94 m3
  3. 0.98 m3
  4. 1.00 m3

Answer: B

11. Size, capacity, and materials need to be specified for

  1. Bib-cocks
  2. Stop-cocks
  3. Ball valves
  4. All the above

Answer: D

12. The weight of an item is measured correctly to the nearest

  1. 0.25 kg
  2. 0.50 kg
  3. 0.75 kg
  4. 1.00 kg

Answer: D

13. Berms are provided in canals if these are

  1. Fully in excavation
  2. Partly in excavation and partly in embankment
  3. Fully in embankment
  4. All the above

Answer: B

14. The expected outturn of half brick partition wall per mason per day is

  1. 1.5 m 3
  2. 2.0 m3
  3. 4.0 m2
  4. 5.0 m2

Answer: B

15. The floor area includes the area of the balcony up to

  1. 100 %
  2. 75 %
  3. 50 %
  4. 25 % 

Answer: C

16. The slope of the outlet of the ‘P trap’ below the horizontal is kept

  1. 8°
  2. 10°
  3. 12°
  4. 14°

Answer: D

Also Read – 100 + Fluid Mechanics MCQ’s | Civil Engineering Interview Questions

Page No- 1 2 3 4 5 6