Estimation and Costing MCQ Questions with Answers | Civil Engineering MCQs – Part 5

Estimation and Costing MCQ Questions with Answers

62. According to the Indian Standards Institute, the actual size of modular bricks is Answer: C 63. The following item of earthwork is not measured separately. Answer: D 64. The measurement is made in square meters in case of Answer: D 65. The area of the cross-section of a road fully in banking shown in … Read more

Estimation and Costing MCQ Questions with Answers | Civil Engineering MCQs – Part 4

Estimation and Costing MCQ Questions with Answers

47. The expected outturn of cement concrete 1 : 2: 4 per mason per day is Answer: D 48. The value of ‘C’ of Indian type W.C. shown in the given figure is: Answer: C 49. The area is measured correctly to the nearest Answer: A 50. The measurement is not made in square meters … Read more

Estimation and Costing MCQ Questions with Answers | Civil Engineering MCQs-Part 3

Estimation and Costing MCQ Questions with Answers

32. Anti-siphonage pipe is connected to Answer: C 33. Pick up the correct statement from the following: Answer: B 34. Pick up the correct statement from the following: Answer: D 35. Pick up the correct statement from the following: Answer: D Also Read – 25+ Indian Compound wall Designs for your Dream House 36. A … Read more

Estimation and Costing MCQ Questions with Answers | Civil Engineering MCQs – Part 2

Estimation and Costing MCQ Questions with Answers

17. The inspection pit or chamber is a manhole provided in a base drainage system Answer: D 18. Pick up the incorrect statement from the following: Answer: C 19. The ‘center line method’ is specially adapted for estimating Answer: D 20. Pick up the incorrect statement from the following: Answer: D 21. The unit of … Read more

Estimation and Costing MCQ Questions with Answers | Civil Engineering MCQs

Estimation and Costing MCQ Questions with Answers

Prepare yourself with these 100+ Estimation and Costing MCQ Questions with Answers. These 100+ Estimation and Costing Interview Questions with Answers will help you in Viva and job interviews. 100+ Estimation and Costing MCQ Questions with Answers 1. The expected outturn for earthwork in excavation in ordinary soil per workman per day is Answer: C … Read more

How to Become a Plumber In 2023(A Guide)

How to become a plumber

Who is a plumber? A plumber is a tradesperson who specializes in installing, repairing, and maintaining systems used for the distribution of water, gas, and sewage in residential, commercial, and industrial buildings. Plumbers typically work with pipes, fixtures, valves, and other plumbing equipment to ensure that water and waste are properly transported and disposed of … Read more

100+ Surveying MCQ Questions | Civil Engineering Interview Questions

100+ Surveying MCQ Questions | Civil Engineering Interview Questions

These 100+ Surveying MCQ interview questions help you to prepare for your job interview and for your competitive exams, you can also get the pdf from the below link. 1. In an internal focussing type of telescope, the lens provided is a) concaveb) convexc) plano-convexd) plano-concave Answer: a 2. Which of the following errors can … Read more

Civil Engineering MCQ’s on Building Materials

Civil engineering MCQ on Building Materials Civil engineering MCQs on building materials with explanation | Basic civil engineering interview questions which were asked in various construction companies and government PWD, GATE, PSU civil engineering jobs interviews. Also get these civil engineering interview questions and answers pdf for free. 41. Pick up the hypabyssal rock from … Read more